Client: Noble Constructors, LLC
Location: Chateaugay, NY 12920
Year Started: 2007
Duration: 11 Weeks
Construction of all access roads and entrances
Construction of 58,000 feet of access roads to Wind Tower Generators
Access roads owned by the State and County were constructed 12’ wide with 14” crusher run base and installation of Geogrid to each tower.
Full time Storm Water Pollution Prevention Plan personnel (SWPPP) on site, entire project SWPPP installation, compliance and maintenance.
Fast paced schedule—project was completed in Six (6) weeks.